John Ross Road Set for Paving

September 29, 2025 By Contributed Article Leave a Comment

The City of East Ridge, in coordination with the Tennessee Department of Transportation (TDOT), announces that construction will begin on the John Ross Road Resurfacing Project  starting Wednesday, October 1. Mobilization will start October 1 followed by milling/resurfacing efforts expected to begin by October 15.

Talley Construction has been selected as the General Contractor for the project, with support from Wright Brothers Construction, WorkZone Traffic Control, and other subcontractors. The project is being managed by Volkert, Inc. The contract allows 60 days of construction, though work is expected to be completed before the end of that timeframe, weather permitting.

Traffic Impacts:

  • Work is scheduled to be completed Monday through Friday, 7:30 a.m. – 5:30 p.m.
  • Drivers should expect alternating lane closures and rolling road closures throughout the duration of the project.
  • A flagging operation will be in place to help direct traffic safely.
  • Crews will first mill down one side of John Ross Road before swapping traffic to complete the opposite side. This same operation will take place during the resurfacing/paving phase. 
Project At-a-Glance:
  • Project: John Ross Road Resurfacing 
  • Contractor: Talley Construction
  • Construction Manager: Volkert, Inc.
  • Subs: Wright Brothers Construction, WorkZone Traffic Control (and others)
  • Start Date: October 1, 2025
  • Work Hours: Monday – Friday, 7:30 am – 5:30pm
  • Traffic: Alternating lane closures, rolling road closures, and flagger operations
  • Contract Time: 60 days 

Filed Under: FEATURED STORY, News, SLIDER

About Contributed Article


Search Our Site

Do you favor the City of East Ridge spending $3 million to install synthetic turf on sports fields at Camp Jordan Park?

View Results

Loading ... Loading ...
  • Polls Archive

Our Sponsors:


Contact Us
Submit A Tip
Copyright Notice
Advertise
Terms of Service
Privacy Policy

Copyright © 2025 · News Pro Theme on Genesis Framework · WordPress · Log in