District 29
HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street):During this reporting period, the contractor will be performing utility relocation work throughout the project limits, installing new drainage structures, and performing initial grading work for retaining wall construction. A traffic shift on I-24 eastbound has been implemented near MM 178 to allow for new construction on the right shoulder of the interstate. Brief intermittent lane closures are possible during daylight hours on SR-2 (Broad St.) and SR-58 (Market St.) to allow for moving equipment and utility relocation.
[Wright Brothers Construction Company, Inc./Wagner/CNU011]
HAMILTON COUNTY I-24 Replacement of Belvoir Ave. bridge over I-24 and I-24 bridges over Germantown Road near MM 183: Single and double alternating lane closures on I-24 EB and WB will be used on 05/06/21 and between 05/09/21 and 05/12/21 from 9 PM and 6 AM. There will be single lane closures in the north and south directions of Germantown Road under the I-24 Bridge and at the intersections of Germantown with North and South Terrace on 05/06/21, 05/07/21, and between 05/03/21 and 05/05/21 from 9 PM and 6 AM.
[Bell and Associates Construction, LP/Blevins/CMGC03]
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction: Phase 2 traffic alignments have been implemented. Watch for trucks entering and exiting project. Traffic should expect multiple lane shifts traveling through the interchange. Lane closures will occur Sunday nights through Thursday nights between 9 PM and 6 AM at the following locations: I-75 NB MM 1, I-75 SB MM 3 and I-24 EB MM 184.0 Traffic pacing may occur throughout interchange Sunday nights through Thursday nights between 9 PM and 6 AM. Additionally, there may intermittent shoulder closures at various locations for access to the median and roadside areas. I-75 NB to I-24 WB split has been moved back 1500 feet from its previous location. Welcome Center traffic intending to use I-24 WB now, will have to detour on I-75 NB to Exit 3. Detailed detour information will be available at the Welcome Center. The speed limit has been reduced to 45 MPH throughout the interchange. Beginning 04/30/2021 at 9 PM the Welcome Center, on I-75 NB, will be closed until 05/24/2021. ***Weekend work scheduled between 05/07/2021 9 PM and 05/10/2021 5 AM on I-75 SB. The contractor will close the right two lanes between MM 3 and MM 2 to complete concrete pavement repairs. Motorists should be aware of heavy work truck traffic during this time. ***
[C.W. Matthews Contracting Company, Inc./Blevins/DB1801]
HAMILTON COUNTY US-27 (I-124) widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge: There are no Mainline Lane Closures for the upcoming period of Thursday, 05/06/21 thru Wednesday, 05/12/21.
[Dement Construction Company, LLC/Curtis/CNP230]
HAMILTON COUNTY SR-27 (MARKET ST.) Utility Work both directions at LM 4.90: Shoulder and single lane closure along Market Street between West 26th Street and Underwood Street. Signage, drums, and cones will be present. Motorists should use caution through the area and be aware of personnel and equipment between 9 AM and 3 PM starting 04/29/21 through 05/12/21. [2021-106]
HAMILTON COUNTY SR-8 (RINGGOLD RD.) Utility Work westbound from LM 1.97 to LM 1.94: Shoulder, bike lane, and single lane closure between Sewanee Drive and San His Drive. Arrow board, signage, drums, and cones will be present. Motorists should use caution through the area and be aware of personnel and equipment between 9 AM and 2 PM starting 05/03/21 through 05/19/21. [2021-280]
HAMILTON COUNTY SR-8 (SIGNAL MOUNTAIN RD.) Utility Work southbound at LM 14.75: Shoulder and single lane closure between Balmoral Drive and Glendale Drive. Signage, flaggers, and cones will be present. Motorists should use caution through the area and be aware of personnel and equipment between 9 AM and 2 PM starting 05/06/21 through 05/12/21. [2021-292]
HAMILTON COUNTY SR-29 (US-27) repair of the bridge over Big Soddy Creek (LM 20.6): The contractor will be performing bridge & roadway repair on the SR-29 bridge over Big Soddy Creek. During this report period the contractor will have one lane of SR-29 north-bound closed. At least one lane of traffic in both directions shall always remain open.
[Mid-State Construction Company, Inc./Osbonlighter/CNU046]
HAMILTON COUNTY SR-2 (US-64, US-11) improvement of the intersection at Edgmon Road in Collegedale (LM 22.7), including grading, drainage and paving:The improvement of the intersection on U.S. 11 (U.S. 64, S.R. 2) at Edgmon Road in Collegedale (L.M. 22.67), including grading, drainage and paving. Extra care should be taken while trucks are entering and exiting the roadway. One lane might be intermittently closed while work is ongoing. The public is advised to be aware of the newly established traffic pattern at the intersection. Additional flaggers will be onsite as needed.
[Talley Construction Company, Inc./Osbonlighter/CNU012]
HAMILTON COUNTY SR-312 resurfacing from south of Henry Road (LM 6.9) to west of SR-58 (LM 14.2): Starting Monday of this reporting period, there will be intermittent lane closures on this road as the Contractor will have flaggers directing traffic for the construction operation. The motoring public should expect possible long delays.
[Wright Brothers Construction Company, Inc./Curtis/CNV087]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, to install power poles and transfer lines. The flagging operations will be performed on 05/06/21, 05/07/21, 05/10/21, 05/11/21, and 05/12/21 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment.
[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]
HAMILTON COUNTY The construction of an S.I.A. to VW: The contractor will be grading, paving, constructing retaining wall(s) and installing signals & lighting on S.I.A. route connecting Ferdinand Piech Way & Volkswagen Dr. The roadway is not open to traffic. The traveling public should be alert to the entrance and exit of construction vehicles from the jobsite onto the connecting roadways. Flaggers may be onsite directing traffic.
[Talley Construction Company, Inc./Osbonlighter/CNU221]